F5 BIG-IP LTM Specialist: Maintain and Troubleshoot (301b) Exam Materials - Question #94 Discussion

Comment Image Comment Image Comment Image

An LTM Specialist receives a replacement device from a Return Material Authorization (RMA). The unit has been racked and powered. The management address has been set, and the OS has been upgraded with the version and hotfix to match the peer. The LTM Specialist needs to restore the base configuration on the LTM replacement. What is the first step the LTM Specialist should take to perform this task? (Choose one answer)

  • A. Force the configuration from the peer
  • B. Configure NTP
  • C. Copy the configuration from the peer
  • D. Load the archive
Correct Answer: D

Brave-Dump Community Votes

Answer: B (1 vote) 100%

Community Explanations & Comments (1)

Anonymous User 7 hours ago
Selected: B
Recommended sequence
1. Configure NTP on the replacement device.
2. Establish device trust with the existing peer.
3. Add the replacement to the device group.
4. Synchronize the configuration from the existing peer to the replacement.