View all questions & answers for the NSE 6 - Network Security 7.6 Support Engineer Materials exam
NSE 6 - Network Security 7.6 Support Engineer Materials - Question #1 Discussion
Community Explanations & Comments (1)
Anonymous User
6 months ago
Selected: B, C
This is Phase 1 negotiation because we have DH is part of SA and since we received the first packet that is why remote is initiator.
Refer to the exhibit. A partial output from an IKE real-time debug is shown. The administrator does not have access to the remote gateway. Based on the debug output, which two conclusions can you draw? (Choose two answers)
Brave-Dump Community Votes