An administrator is attempting to create two static routes: one for the SD-WAN zone wan-link and one pointing to a specific SD-WAN member interface that currently belongs to the wan-link zone. Which configuration is required to make this scenario valid? (Choose one answer)

  • A. The destination subnets of the two static routes must be different.
  • B. Both routes must have the same administrative distance to allow equal-cost multi-path (ECMP).
  • C. The destination subnet configured on the SD-WAN zone cannot be a default route.
  • D. SD-WAN member must be an IPsec interface.
Correct Answer: B

Brave-Dump Community Votes

Answer: A (2 votes) 100%

Community Explanations & Comments (2)

Anonymous User 2 months ago
Selected: A
The use case for A is to give preference to the member for this destination.
ab 1 month ago
Selected: A
A